Bond Funds Will Accomplish the Following Work

  • Replace the Johnson Road station with a new fire station including but not limited to: The total estimated cost for this project is $8,352,165
  • Demolition of existing building.
  • Structural fill of basement
  • Relocate Overhead service to cell tower
  • Construct new fire station
  • Emergency generator for entire building
  • All site work
  • Outdoor signage
  • Technology, furniture and fixtures, all other amenities.
  • External pole barn
  • All soft costs
  • Renovation to the East Holly Ave. and Hurffville-Grenloch Road fire station including but not limited to: The total estimated costs for these upgrades is $1,015,750
  • East Holly Avenue:
  • Upgrade sleeping quarters for firefighters
  • Upgrade existing toilet facilities to include showers and most recent ADA compliance
  • Install 2 new toilet/shower rooms
  • Fitness room upgrades
  • Gear room upgrades to include ventilation
  • Upgrade parts of the HVAC system and new security door
  • Hurffville-Grenloch Road:
  • Upgrade sleeping quarters for firefighters
  • Upgrade to HVAC system
  • New gear room with ventilation
  • Training mezzanine
  • Roof Replacement
  • Other fire district wide projects as shown below. Total estimated costs for these upgrades is $600,548.
  • Replace damaged aprons throughout district.
  • Mill and replace parking lot area at headquarters
  • HVAC systems repair/upgrades
  • Vehicle exhaust systems for stations